Beaver is a 500 megawatt combined-cycle natural gas plant and one 24.8 megawatt steam turbine
Operating since 1976. The plant is exempt from the site certificate requirement because construction began before the enactment of Oregon´s energy facility siting law. The generating capacity of Unit 8 is below the jurisdiction of the Council.
Columbia County
Applicant/Certificate holder: Portland General Electric
Applicant/Certificate holder contact: Arya Behbehani
​​​​​​​​​​

Project Timeline

​​
  
Additional Documents
  
500 MW Beaver Power Plant began operation
01/01/1976
Unit 8 Began Operation
08/01/2001
​​
​​​​​​​​​​​​​​​​​​​
​Contact the Facility Siting Team:
​​​​​​​​​​​​​​​
​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​​

Exhibit Files Reference

  • Exhibit A: Applicant Information 
  • Exhibit B: Project Description
  • Exhibit C: Property Location and Maps
  • Exhibit D: Organizational Information
  • Exhibit E​: Permits Required
  • Exhibit F: Property Ownership 
  • Exhibit G: Materials Analysis
  • Exhibit H: Geology and Soil Stability 
  • Exhibit I: Soils
  • Exhibit J: Wetlands
  • Exhibit K: Land Use
  • Exhibit L: Protected Areas
  • Exhibit M: Financial Analysis
  • Exhibit N​: Non-generating Facility Information
  • Exhibit O: Water Requirements
  • Exhibit P: Fish Wildlife Habitat 
  • Exhibit Q: Threatened and Endangered Plants and Animals
  • Exhibit R: Scenic Aesthetic Values 
  • Exhibit S: Cultural Resources
  • Exhibit T: Recreational Facilities 
  • Exhibit U: Public Services
  • Exhibit V​: Waste Minimization 
  • Exhibit W: Site Restoration
  • Exhibit X: Noise 
  • Exhibit Y: Carbon Dioxide Emissions 
  • Exhibit Z: Cooling Towers  
  • Exhibit AA: EMFs – Electric and Magnetic Fields
  • Exhibit BB: Other Information
  • Exhibit CC: Additional Statutes Rules Ordinances
  • Exhibit DD​: Other Specific Standards