If you have determined that you are required to submit a CAO Permit Modification AQ502 Form for proposed changes at your facility (see FAQ, “How are permit modifications handled under CAO"), the following fees may apply.
- Re-evaluation of Risk Assessment may require the following Specific Activity Fees:
- TEU Risk Assessment[1] – no permit mod (#16)
- TEU Risk Assessment – permit mod (#17)
- Level 2 Modeling review only for TEU approval (#18)
- Level 3 Modeling review only for TEU approval (#19)
- Source Test Review Fee (plan and data review) – simple to complex (#23-#25)
- Community Engagement Meeting Fee – low to high (#20-#22)
- TBACT/TLAER Review (per Toxic Emissions Unit and type of Toxic Air Contaminant) (#15)
- If a permit modification is required based on the results of the revised Risk Assessment, then the applicable Toxic Air Contaminant Permit Addendum (TACPA) modification fee [OAR 340-216-8020 Table 2, Part 4] must also be submitted - please refer to OAR 340-245-0100(8)(f)&(g), or consult with DEQ to determine the appropriate fee:
- Basic/Non-technical Fee
- Moderate Technical Fee
- Complex Technical Fee
Below are examples of fee requirements for different cases where a facility is proposing modifications after previously completing an approved Risk Assessment under CAO. Please consult with CAO staff if you need further clarification.
Example 1: Constructing new TEUs with increase in risk but not above previous Risk Action Level
An existing source that was previously issued a TACPA (i.e., not determined to be an Exempt or De minimis source) after completing a Risk Assessment is proposing to add two new Significant Toxics Emissions Units (TEUs) that emit Toxic Air Contaminants (TACs). The facility is submitting a revised Level 3 Risk Assessment that demonstrates a minor increase in risk, but that does not cause the source risk to exceed the previous Community Engagement Risk Action Level (RAL). The following fees apply:
- Moderate Technical TACPA fee – because the addition of new TEUs likely requires new permit conditions, but the risk did not exceed a higher RAL than the original Risk Assessment.
- TEU Risk Assessment fee[1] – permit mod (Specific Activity fee #17)
- Level 3 Modeling review only for TEU approval (Specific Activity fee #19)
- Community Engagement Meeting Fee – low (Specific Activity fee #22) – because DEQ previously required a community meeting when the original TACPA was issued, and will only require mailing a postcard for this modification.
Example 2: De minimis source constructing new TEUs, new risk exceeds Toxics Lowest Achievable Emission Rate RAL
A new source that was previously determined to be a de minimis source is proposing to add seven new TEUs (three “Type A" TEUs and four “Type B" TEUs) - previously this source was only operating one “Type A" TEU. The submitted Risk Assessment indicates the risk is above the Toxics Lowest Achievable Emissions Rate (TLAER) RAL. The following fees apply:
- Complex Technical TACPA fee
- TEU Risk Assessment fee – permit mod (Specific Activity fee #17)
- Level 3 Modeling review only for TEU approval (Specific Activity fee #19)
- Community Engagement Meeting Fee – high (Specific Activity fee #22) – DEQ would require a community meeting
- TBACT/TLAER Review (per Toxics Emissions Unit and type of toxic air contaminant) (Specific Activity fee #15) – this fee will be required each for “Type A" and “Type B" TEUs, and once again as the emit both volatile TACs and particulate heavy metal TACs, requiring separate control technologies for each type of TAC.
Example 3: Source testing data used to update production limits
An existing source performs source testing that demonstrates the TAC emission estimates used in the Risk Assessment were much higher than observed in the site-specific test results. The testing required more than one test method be performed to obtain these results. The source submits a revised Level 3 Risk Assessment using the new emissions data, along with increased activity levels for the TEU. This increased activity is greater than the levels allowed under the current permit but does not increase risk above the original Risk Assessment, which was below the Community Engagement RAL. The following fees apply:
- Basic Technical TACPA fee
- TEU Risk Assessment fee – permit mod (Specific Activity fee #17)
- Level 3 Modeling review only for TEU approval (Specific Activity fee #19)
- Source Test Review Fee (plan and data review) – moderate (Specific Activity fee #24) – this is a moderate fee because it was a single TEU that required multiple testing methods.
Example 4: Constructing new TEUs, risk does not exceed de minimis RAL
A new source was determined to be a de minimis source based on its approved Level 1 Risk Assessment. This source is proposing to add a new TEU and submits a revised Level 1 Risk Assessment that demonstrates that the risk does not increase above the de minimis RAL (note: all TEUs must be modeled at capacity [see OAR 340200-0020(19) & OAR 340-245-0020(14)]). The following fees apply:
- No TACPA fee required
- TEU Risk Assessment fee – no permit mod (Specific Activity fee #16)
[1] – For the purposes of the review of revised Risk Assessments for changes proposed at facilities, the Specific Activity fees #16 and #17 can refer either to a single TEU review or a facility-wide risk re-evaluation.