The Emissions Inventory provides information on all the Toxic Air Contaminant emissions from a facility, and includes information on a facility’s operations and activities, as well as fuel and material usage rates. This is often the longest step in the CAO risk assessment process as DEQ needs to verify that all activities have been accounted for, and that the most representative emissions data available are used. In some cases, DEQ will require a facility to perform source testing at this stage if insufficient data is available to estimate emissions.
For an introduction to emissions inventories and why they matter, please see EPA's
Fact Sheet. A facility-specific emissions inventory timeline and associated documents are linked below.
Feb. 1, 2022: Facility called in to CAO program.
April 15, 2022: Facility submitted Emissions Inventory extension request.
April 19, 2022: DEQ responded to Emissions Inventory extension request.
May 16, 2022: Facility submitted the Emissions Inventory
Nov. 8, 2022: DEQ responded to the Emissions Inventory submittal with a request for revisions and additional information.
Dec. 12, 2022: Facility submitted Emissions Inventory extension request.
Dec. 21, 2022: DEQ responded to Emissions Inventory extension request.
Jan. 11, 2023: Facility submitted revised Emissions Inventory.
Jan. 13, 2023: Facility submitted a source test plan for the main foundry and cooling bunker areas.
Jan. 24, 2023: DEQ issued a response requiring revisions to the source test plan for the main foundry and cooling bunker areas.
Feb. 7, 2023: Facility submitted a revised source test plan for the main foundry and cooling bunker areas.
Feb. 13, 2023: DEQ approved the source test plan for the main foundry and cooling bunker areas.
Feb. 16, 2023: Facility submitted a source test plan for total enclosure verification for the cutoff and grinding areas.
Feb. 23, 2023: DEQ approved the source test plan for total enclosure verification for the cutoff and grinding areas.
March 10, 2023: Facility submitted an extension request.
March 13, 2023: DEQ responded to the extension request.
May 15, 2023: Facility submitted a source test report for total enclosure verification for the cutoff and grinding areas.
May 18, 2023: Facility requested and received an extension of the deadline to submit the source test report for the main foundry and cooling bunker areas.
May 25, 2023: Facility requested and received an extension of the deadline to submit the source test report for the main foundry and cooling bunker areas.
June 2, 2023: DEQ issued a source test review report for the April 18, 2023 total enclosure verification testing for the cutoff and grinding areas.
June 15, 2023: Facility submitted a source test report for additional total enclosure verification testing for the cutoff and grinding areas.
June 16, 2023: Facility submitted a source test report for the main foundry and cooling bunker areas.
June 22, 2023: DEQ issued a source test review report for the April 18 and June 1, 2023 total enclosure verification testing for the cutoff and grinding areas.
July 27, 2023: DEQ requested updates to the source test report for the main foundry and cooling bunker areas.
Aug. 11, 2023: DEQ responded to the January 11, 2023 Emissions Inventory submittal with a request for revisions and additional information.
Aug. 28, 2023: Facility submitted a revised source test report for the main foundry and cooling bunker areas.
Oct. 4, 2023: DEQ requested updates to the source test report for the main foundry and cooling bunker areas.
Nov. 20, 2023: DEQ approved the source test data for the main foundry and cooling bunker areas.
Dec. 12-13, 2023: Facility requested and received an extension of the deadline to submit the revised Emissions Inventory.
Jan. 10, 2024: Facility submitted a revised Emissions Inventory
Aug. 9, 2024: DEQ responded to the revised Emissions Inventory submittal with a request for revisions and additional information.