Project
The project focuses on upgrading the park and campground utilities, including power and water lines. The upgrades include:
- Replacing single-phase power to three-phase power so onsite equipment can operate safely.
-
The local power provider will also replace the overhead power lines with underground power lines in conduit.
- Replacing portions of the water lines that are well beyond replacement age and are an ongoing maintenance issue.
Temporary Visitor Impact
The park reopened Aug. 1, 2024 after an 11-month closure for construction.
Milestones
- Substantial completion of construction.
- Awarded construction contract to Laskey-Clifton and started construction.
Design finalized.
Next Steps
- Completion of the water line to the shop, group
camp, hiker/biker and lift station
- Permanent electrical equipment installed.
The current general obligation bond estimate is $5-6 million.
Last updated Aug. 2024. Additional updates as information becomes available.