About
The historic Luckiamute River Bridge was built in 1928 and was part of the old highway replaced by OR 99W/Pacific Highway West. It is located on Helmick Road, which is the primary route for farming vehicles and a common detour for traffic along OR 99W.
The bridge is in poor condition and needs repairs.
We're planning to perform maintenance and bridge strengthening work, which includes:
• Making the bridge earthquake ready.
• Cleaning and painting.
• Sealing the driving surface.
The work will preserve the history of the bridge and make it safe for years to come.
Schedule
Design: 2023 - 2025
Construction: 2026 - 2027
Location
N/A
|
Helmick Road | Polk County
Cost and Funding
Design: $698,300
Construction: $3,079,500
Pedestrians, including those with disabilities, will have access through or around work zones.