About
Whether you drive, ride, walk or roll, we are committed to providing the best accessibility possible to all people using the transportation system.
One of the ways we are doing this is by bringing curb ramps along our highways to current American with Disabilities Act (ADA) accessibility standards.
As part of this effort, we are exploring ways to design and construct these ramps more efficiently.
For this project, we will rebuild or install new curb ramps in various locations along OR 18B.
Schedule
Design: 2023-2024
Construction: 2025
Location
OR 18B
|
Willamina | Milepost 2 to 2.7
Sheridan | Milepost 5.9 to 7.6
Cost and Funding
Total budget: $8 million
Pedestrians, including those with disabilities, will have access through or around
the work zone.