OR 99 Seismic Bridge Retrofit

Construction Phase

Region 3: Southwestern Oregon (Gold Hill, Grants Pass, Rogue River, Jackson, Josephine)


​​​​​​​​​​​​​Southern Oregon Seismic Bridge Retrofit Project at Birdseye Creek, Foots Creek and Millers Gulch Creek


Slow down, in the work zone it could save lives. Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time, try a new way or mode to get there or take a different route.

Impacts

Traffic Impact

​This project will impact traffic patterns on OR 99 and I-5.

Construction Impacts

The contractor has completed the work at all three bridges for the year. Anticipating work to continue Spring 2025 at Foots Creek Bridge. 

For updates - visit Trip Check​

Schedule

​Estimated Construction Dates:  Nov 2023 - June 2025

Details

Location

Multiple |

​OR 99 - Rogue River Hwy MP 10.8 - 12.2. View Project Area Map​

Cost and Funding

​$11 Million

Contractor

​Project Contractor:  Carter & Company Inc. 

Consultant:  DOWL

Benefits

​Project Information:  

  • The project will replace bridge structures at the 3 locations for earthquake resilience.
  • The estimated construction dates are Nov 2023 – June 2025.
  • The estimated cost is $11 million.
  • The construction will close the bridges to all vehicle traffic for a portion of the project.

Contacts & Media

Millers Gulch Bridge Completed

Image Gallery

Project Contacts

Public Information Officer
Mary Elizabeth Dillinger
Email
Mary.Dillinger@ODOT.Oregon.gov
Phone
541-621-3074

Consultant Project Manger
Roger Thom
Email
Roger.Thom@odot.oregon.gov
Phone
541-499-9862

Get Project Alerts

Sign up for the newsletter!

Last Updated

11/6/2024 3:24 PM

Project Number

22290