OR 99W: Ross Island Bridge to SW Wills Lane and U.S. 30B: Kerby Avenue to Northeast 165th Avenue

Design Phase

Region 1: Portland metro and Hood River County (Portland, Multnomah)


​​​​All Roads Transportation Safety Program (ARTS) projects improve safety at over 200 intersections on major roads in the Portland metro area. ​​​​

Impacts

Traffic Impact

Construction areas will have short-term daytime and nighttime single-lane closures. Sidewalks, paths, bike lanes and crosswalks will have signed detour routes. ​More information about expected traffic impacts will be provided closer to construction.​ 
​​

Construction Impacts

Information about current traffic impacts during construction will be updated on this project webpage.

Closures and Detours 
When construction begins, travelers should expect daytime and nighttime single-lane closures in construction areas. Work that impacts sidewalks, paths, bike lanes, or crosswalks will have signed detour routes.

Noise
​To minimize traffic impacts during the day, some night work is required. Those working or living in the area may hear heavy equipment, construction trucks, a beeping noise when vehicles are in reverse (required by the Occupational Safety and Health Administration) and equipment such as concrete saws, drills and jackhammers. 

More information will be provided to residents and businesses in the project area before construction begins, including a noise hotline to call for help resolving noise-related concerns 24 hours a day. The noise hotline number will be posted to this webpage.

Schedule

Construction is anticipated to begin in early 2025 and will continue through summer 2025.​​

The project schedule is subject to change. 


Details

About

​​​​​​The All Roads Transportation Safety Program​ (ARTS) identifies intersections where a high concentration of crashes occur and then implements safety improvements to help reduce crashes at these locations.

Safety improvements along OR 99W from Ross Island Bridge to SW Wills Lane and along U.S. 30 Bypass from North Kerby Avenue to Northeast 165th Avenue include:
  • Adding or upgrading “S​top” signs and street name signs on intersection side streets.
  • Adding stop bar pavement markings on intersection side streets.
  • Adding bicycle lane markings on the road for better visibility at areas where bicycles and vehicles share the road.​
  • Upgrading existing traffic signal heads to make them larger and more reflective to increase visibility.
​Other improvements may inclu​de signage, enhanced pavement markings and traffic signal improvements.

Project Area​​​
(Click on ima​ge of map to open in a new tab)​

A full list of intersection locations and work descriptions on OR 99W and U.S. 30 Bypass is available ​here.

Location

OR 99W |

OR 99W from Ross Island Bridge to SW Wills Lane

US 30B ​|​​ US 30B from North Kerby Avenue to Northeast 165th Avenue

Cost and Funding

​Project cost: $2,470,797​

Contractor

​​We will provide the contractor once selected.

Additional Information

For ADA (Americans with Disabilities Act) or Civil Rights Title VI accommodations, translation/interpretation services, or more information call 503-731-4128, TTY 800-735-2900 or Oregon Relay Service 7-1-1.​

Si desea obtener información sobre este proyecto traducida al español, sírvase llamar al 503-731-4128. 

Если вы хотите, чтобы информация об этом проекте была переведена на русский язык, пожалуйста, звоните по телефону 503-731-4128. 

Nếu quý vị muốn thông tin về dự án này được dịch sang tiếng Việt, xin gọi 503-731-4128.​ 

이 프로젝트에 관한 한국어로 된 자료 신청방법 전화: 503-731-4128. 

如果您想瞭解這個項目翻譯成繁體中文的相關資訊,請致電 503-731-4128. 

如果您想了解这个项目翻译成简体中文的相关信息,请致电503-731-4128.

Contacts & Media

Project Contact

Community Affairs Coordinator
Dee Hidalgo
Email
dee.hidalgo@ODOT.oregon.gov
Phone
503-731-8230

Get Project Alerts

Sign up for the newsletter!

Last Updated

11/1/2024 12:55 PM

Project Number

21616

Project Documents

Related documents to this project
ARTS OR99W and US 30_Factsheet (August 2023)21616.pdfView this factsheet for more details about this project.
ARTS-OR99W-US30-2023-Noise-Variance-Postcard-21616.pdfARTS OR99W US30 Noise Variance Postcard
Intersection Work Locations (September 2024).pdfA full list of intersection locations and work descriptions on OR 99W and U.S. 30 Bypass.