About
U.S. 101 and U.S. 101B are heavily used highways in Astoria and Warrenton.
Some of the signs along the highways were worn and outdated and needed to be replaced.
We replaced the damaged signs with new ones that meet current standards.
These new signs will help make the area safer, allowing you to have an easier time to know the speed limit and see upcoming landmarks and destinations.
Schedule
Design: 2022 - 2024
Construction: 2024 - 2025
Location
Multiple
|
U.S. 101 | Milepost 0 to 3.8 and milepost 4.6 to 5.2
U.S. 101B | Milepost 5.7 to 7.1
Cost and Funding
Design and construction: $545,384
Pedestrians, including those with disabilities, will have access through or around work zones.