U.S. 101 Paving (SE 40th Street to SE 123rd Street)

Construction Phase

Region 2: Willamette Valley and Northwest Oregon (Newport, Lincoln)


​​​​​​​​​We are repaving to preserve the road and give you a smoother ride.​


Banner: Slow down, in the work zone it could save lives. Building a modern transportation system to help Oregon’s communities and economy thrive. During construction, Give yourself more time, try a new way or mode to get there or take a different route.

Impacts

Traffic Impact

​None at this time, we plan to start work in June.

Construction Impacts

​None at this time. We plan to start work in June.

During construction you can expect brief lane closures with flaggers helping direct traffic through the work zone.

Construction Activities

​None at this time. 

Visit TripCheck​ for the most current traffic information.​


​Pedestrians, including those with disabilities, will have access through or around work zones. ​


work zone construction iconPay attention in the work zone, slow down and move over – imagine this is where you work! 

Always drive safely, watch for construction signs and workers. 

Remember: fines double in all Oregon work zones, whether workers and signs are present or not. 

Details

About

Enlarged Project Area MapThe pavement in this section of U.S. 101 is in poor condition and needs to be replaced. 

For this project, we're planning to:

  • Repave the road. 
    • This will help reduce maintenance costs and give you a smoother ride.
  • ​Install new striping and rumble strips. 
    • Striping helps clearly define each travel lane. Rumble strips provide noise and vibration to alert a driver when they’re leaving their lane.
  • Build ADA curb ramps at SE 40th Street. 
    • ​These curb ramps help make it easier for everyone to move between the curb and road, whether you have a disability or not.

Schedule

Design: 2022 - 2024
Construction: 2024 - 2025

Location

U.S. 101 |

​Milepost 142.5 to 147 | Between SE 40th Street and SE 123rd Street

Cost and Funding

Total cost: $4,844,331

Contacts & Media

Project Area Map

Project Contacts

Resident Engineer
Steve Schultz
Email
steven.schultz@odot.oregon.gov
Phone
541-757-4211

Public Information Officer
Mindy McCartt
Email
mindy.m.mccartt@odot.oregon.gov
Phone
503-507-6045

Get Project Alerts

Sign up for the newsletter!

Last Updated

4/3/2025 4:20 PM

Project Number

21546