About
There have been several previous Beltline Highway construction projects
in the recent past. This project completed many elements that were not able to be completed with the prior projects.
Project improvements included:
A new bus pullout at Green Hill Road.
A repaved and repaired highway surface.
New signs to meet current standards.
Modified traffic signals at various intersections.
ADA improvements to meet current standards.
Bridge repairs.
A new concrete median from Roosevelt Boulevard to Coburg Road.
Camera, traffic sensor and variable message board sign installations at various locations.
Schedule
Design: 2019-2021
Construction: completed July 2024
Location
OR 569
|
Between Green Hill Road and Coburg Road (mileposts 1.2-11.7)
Cost and Funding
$15,381,600