Skip to main content

Oregon State Flag An official website of the State of Oregon »

Project-Details







Medford, Jackson County Foothill Road Improvement Project

Construction Phase

Region 3: Southwestern Oregon (Medford, Jackson)


​​​​​​​​​​​​​​​​​​​​​​​​​​​Improves safety and modernizes nearly four miles Foothill Road in east Medford​ and Jackson County


Impacts

Traffic Impact

​New Traffic Alert:

2024 Foothill Road Closure June.jpgFoothill Road Closure Map - Local Access Resize.jpgFoothill Road Improvements Resize_1.jpg 

Full Closure:  Foothill Road from Cedar Links Drive to McAndrews Road

Foothill Road from Cedar Links Drive to McAndrews Road Westbound ramp is closed until Summer 2024. This closure will allow contractors to rebuild and widen the road. 

Detours using Cedar Links Drive to Springbrook Road to East McAndrews Road are available. Local access will be available from Cedar Links Drive. 

Normil Terrace residents can access their homes at all times by entering from Cedar Links Drive (see map). 

​Thank you for your patience! ​​

Project information and current construction schedule (subject to change) is available at: FoothillRoadProject.org


Sign up for project updates by emailing Jayda McClendon at:  JTMcClendon@cityofmedford.org

Meantime, all project updates and news releases will be posted on this website. Thanks !!​


Construction Impacts

Latest Update Provided by​ Jackson County on July 12, 2024:

The next FULL CLOSURE, which will close Foothill Rd. between Coker Butte Rd. and Dry Creek Rd. will begin on the morning of Monday, July 15, 2024 thru the end of August/early September 2024. Recommend travelers use an alternate route. Detours will be available using E. Vilas Road, Crater Lake Avenue and Coker Butte Road. Residences on Dry Creek Road will have continuous access to and from Foothill Rd. on the north side fo the closure throughout the entire duration of the closure.  

Latest Update Provided by the City of Medford on July 3, 2024:

Stage 3 – Phase 2 (McAndrews/Lone Pine to Normil Terrace) - Closed to Traffic

Fencing for Walls M, N, L and P1 continues. Final paving adjustments made. Concrete islands and traffic separators will be installed next week. Paving and sidewalk work continues.   

Stage 3 – Phase 3 (Normil Terrace to Cedar Links) - Closed to Through Traffic, Local Access Only

​Drilling and installation of piles continues for Wall “D-G." Installation of lagging panels continues. Excavation continues as well.

Stage 4 – Cedar Links to Delta Waters

The 24" welded steel water line was completed on Viewpoint Drive, and the trench paved.

The 12" waterline on Foothill was also completed.

Tie ins for both the 24" and 12" water mains remain (to make active). 

Foothill Paving.jpg
Foothill_Hillcrest.jpg

What is ahead

Traffic will be switched over to enter the construction area from the south, by McAndrews; local access only to Normil Terrace this month. Foothill Road will continue to be closed to through traffic. There is a lot of work to be completed on Stage 3 from Normil Terrace to Cedar Links Drive. The active construction will close Normil Terrace to Cedar Links.  

Stage 3 – Phase 2 (McAndrews/Lone Pine to Normil Terrace) - Closed to Traffic

Coping of “J2" and “J1" is scheduled to be poured through July 8. Sidewalk continues. Traffic Islands are scheduled for the week of July 12.​

Construction Activities

​​Major construction of this two lane road will affect traffic flow. Drivers should use alternate routes to get to their destinations, especially during full closures of the roadway.

Meetings and Events

​Various ​meetings have been held by both Medford and Jackson County. A mailing has been sent to Jackson County and City of Medford residents near the project area prior to construction of the respective sections.


Schedule

​Construction expected between January 30, 2023 through 2026.

Details

About

​Within Medford, this modernization and safety project widens two miles of Foothill Road between Hillcrest and Delta Waters Roads to an urban standard for safety and future capacity.

In most sections, the current two-lane roadway will be widened to five lanes, with a center turn lane, curb, gutter, sidewalk and bike lanes.

Constructs a 1,000 foot section of the new South Stage Road off North Phoenix Road.

The Jackson County portion is from Dry Creek Road south to Delta Waters Road. 

This safety project will construct two lane roadway with multi-use shoulders with center turn lanes at Dry Creek, Coker Butte and Devils Garden Roads.

The project will straighten and improve the existing hills and curves in the area near Dry Creek and Coker Butte Roads. 

ODOT is inspecting this project and handling contract administration in coordination with the City of Medford. 

Location

N/A |
  • ​Jackson County: Dry Creek Road south to Delta Waters Road
  • Medford: Delta Waters Road south to Hillcrest Road.
    • 1000' of the new South Stage Road segement will also be constructed.  

Cost and Funding

Medford Section

(Hillcrest Rd. to Delta Waters Rd.)

Project Cost: ~$62.6 M

Includes a Federal BUILD Grant: $15.5M

 

Jackson County Section

(Delta Waters Rd. to Dry Creek Rd.) 

Project Construction Cost:  $11M

Contractor

​Knife River Materials of Central Point on both the Jackson County and City of Medford portions of this project.

Benefits

​Improves safety and modernizes a key regional Rogue Valley route on the east hills of Medford for current and future growth.

The corridor also upgrades the former two lane county road between Oregon 140 to the north and Interstate 5 at Phoenix to the south.

What Problem Will This Improve?

​Improves safety and upgrades a two lane country road with no shoulders to an urban standard to meet today and future needs. 

Additional Information

​​Any questions about the project, please contact Jayda McClendon at:  JTMcClendon@cityofmedford.org or Mary Dillinger at Mary.DILLINGER@odot.oregon.gov​


News Release:

Foothill Road Closure- July 31_Late Fall 2023 graphic:FoothillRoadFullClosureJuly31ThruLateFall2023.jpg

Medford Foothill Road Project Begins_Feb17_final.pdf

Project design over aerial in four stages. ((Large files and may take some time to download, depending on internet speed):

Stage 1: McAndrews Road interchange area:

P1825 Overall w_Aerial-Stage I.pdf

Stage 2: Hillcrest to McAndrews Road:

P1825 Overall w_Aerial-Stage II.pdf

Stage 3: McAndrews north to Cedar Links:

P1825 Overall w_Aerial-Stage III.pdf

Stage 4: Cedar Links to Delta Waters Road:

P1825 Overall w_Aerial-Stage IV.pdf

Medford Foothill Road Project_final.pdf

JacksonCo Foothill Road Project_final.pdf

Foothill Road_McAndrews to Hillcrest_Typical Cross Section.pdf

JacksonCo_FoothillProject_ DryCreek2DeltaWatersRoadExhibit.pdf

Jackson Co Foothill Road_ Typical Cross Section.jpg

Contacts & Media

Videos


View on YouTube

Image Gallery

Project Contacts

Communication Specialist - City of Medford
Jayda McClendon
Email
JTMcClendon@cityofmedford.org
Phone
541-774-2008

Public Information Officer
Mary Elizabeth Dillinger
Email
Mary.Dillinger@ODOT.Oregon.gov
Phone
541-621-3074

Last Updated

7/12/2024 2:22 PM

Project Number

19231

Project Documents

Related documents to this project
Medford Foothill Road Project_final.pdfGraphic of the Medford Foothill Road Improvement Project
Medford DeltaWater sMcAndrews_AerialwithDesign_LargePDF_from City of Medfordt1.pdfA cross section design over aerial of the future Foothill Road improvement sin the City of Medford - large file.
FoothillRD_McAndrews to Hillcrest_Open House Cross Section.pdfA typical cross section graphic of the Foothill Road improvements between McAndrews and Hillcrest Roads
Foothill Road_McAndrews to Hillcrest_Typical Cross Section.pdfA graphic illustraton of a typical cross section of Foothill Road between McAndrews Road and Hillcrest Road in the City of Medford.
JacksonCo_FoothillProject_ DryCreek2DeltaWatersRoadExhibit.pdfIllustration of the roadway cross seciton of Foothill Road between Delta Waters Road and Dry Creek Road in Jackson County.