Traffic Impact
New Traffic Alert:
![2024 Foothill Road Closure June.jpg](/odot/Projects/SiteAssets/Lists/Project%20List/EditForm/2024%20Foothill%20Road%20Closure%20June.jpg)
![Foothill Road Closure Map - Local Access Resize.jpg](/odot/Projects/SiteAssets/Lists/Project%20List/EditForm/Foothill%20Road%20Closure%20Map%20-%20Local%20Access%20Resize.jpg)
Full Closure: Foothill Road from Cedar Links Drive to McAndrews Road
Foothill Road from Cedar Links Drive to McAndrews Road Westbound ramp is closed until Summer 2024. This closure will allow contractors to rebuild and widen the road.
Detours using Cedar Links Drive to Springbrook Road to East McAndrews Road are available. Local access will be available from Cedar Links Drive.
Normil Terrace residents can access their homes at all times by entering from Cedar Links Drive (see map).
Thank you for your patience!
Project information and current construction schedule (subject to change) is available at: FoothillRoadProject.org
Sign up for project updates by emailing Jayda McClendon at: JTMcClendon@cityofmedford.org
Meantime, all project updates and news releases will be posted on this website. Thanks !!
Construction Impacts
Latest Update Provided by Jackson County on July 12, 2024:
The next FULL CLOSURE, which will close Foothill Rd. between Coker Butte Rd. and Dry Creek Rd. will begin on the morning of Monday, July 15, 2024 thru the end of August/early September 2024. Recommend travelers use an alternate route. Detours will be available using E. Vilas Road, Crater Lake Avenue and Coker Butte Road. Residences on Dry Creek Road will have continuous access to and from Foothill Rd. on the north side fo the closure throughout the entire duration of the closure.
Latest Update Provided by the City of Medford on July 3, 2024:
Stage 3 – Phase 2 (McAndrews/Lone Pine to Normil Terrace) - Closed to Traffic
Fencing for Walls M, N, L and P1 continues. Final paving adjustments made. Concrete islands and traffic separators will be installed next week. Paving and sidewalk work continues.
Stage 3 – Phase 3 (Normil Terrace to Cedar Links) - Closed to Through Traffic, Local Access Only
Drilling and installation of piles continues for Wall “D-G." Installation of lagging panels continues. Excavation continues as well.
Stage 4 – Cedar Links to Delta Waters
The 24" welded steel water line was completed on Viewpoint Drive, and the trench paved.
The 12" waterline on Foothill was also completed.
Tie ins for both the 24" and 12" water mains remain (to make active).
![Foothill Paving.jpg](/odot/Projects/SiteAssets/Lists/Project%20List/EditForm/Foothill%20Paving.jpg)
![Foothill_Hillcrest.jpg](/odot/Projects/SiteAssets/Lists/Project%20List/EditForm/Foothill_Hillcrest.jpg)
What is ahead
Traffic will be switched over to enter the construction area from the south, by McAndrews; local access only to Normil Terrace this month. Foothill Road will continue to be closed to through traffic. There is a lot of work to be completed on Stage 3 from Normil Terrace to Cedar Links Drive. The active construction will close Normil Terrace to Cedar Links.
Stage 3 – Phase 2 (McAndrews/Lone Pine to Normil Terrace) - Closed to Traffic
Coping of “J2" and “J1" is scheduled to be poured through July 8. Sidewalk continues. Traffic Islands are scheduled for the week of July 12.
Construction Activities
Major construction of this two lane road will affect traffic flow. Drivers should use alternate routes to get to their destinations, especially during full closures of the roadway.
Meetings and Events
Various meetings have been held by both Medford and Jackson County. A mailing has been sent to Jackson County and City of Medford residents near the project area prior to construction of the respective sections.
Schedule
Construction expected between January 30, 2023 through 2026.