The culvert is located on OR 6 at milepost 9.93 in Tillamook county. The failing portion is very deep under the roadway in soil that isn't heavily compacted. We are developing alternatives to replacing the failing pipe.
Proposed solutions must restore the stream to its natural path to accommodate fish passage from Wilson River upstream along Zig Zag Creek.
We're
designing this project but are not yet funded for construction.
Schedule
The project is currently in design.
Construction is not scheduled.
Location
OR 6
|
Zig Zag Creek
Cost and Funding
Design: $676,000
Construction: not currently funded
Pedestrians, including those with disabilities, will have access through or around the work zone.