Project
The project focuses on upgrading the park and campground utilities, including power and water lines. The upgrades include:
- Replacing single-phase power to three-phase power so onsite equipment can operate safely.
-
The local power provider will also replace the overhead power lines with underground power lines in conduit.
- Replacing portions of the water lines that are well beyond replacement age and are an ongoing maintenance issue.
Temporary Visitor Impact
Scheduling requires the park closed Sept. 5, 2023 through Spring 2024.
Milestones
- Design finalized.
- Awarded construction contract to Laskey-Clifton and started construction.
Next Steps
- Substantial completion of construction in June 2024.
The current general obligation bond estimate is $5-6 million.
Last updated March 2024. Additional updates as information becomes available.