Summer 2009 Road Projects
Interstate 5 Road Project Hotlines
Interstate 84
U.S. Highways
Oregon Highways
Other Roads
Portland Area Projects
Interstate 5

/ODOT/COMM/images/2009ConstMap-550.jpg1.  I-5 Pacific Highway — Widen to three lanes, add shoulders from Victory Boulevard to Lombard Street (Delta Park Project). Nighttime lane closures. Completion: 11/2010. 
2. I-5 Pacific Highway — Pave from MP 289.8 to 283 (Tualatin River to Willamette River), widen Nyberg Road off-ramp from I-5 south, add north and southbound auxilliary lanes, build new sound wall. Nighttime lane closures. Completion: 12/2010.
 
3. I-5 Pacific Highway — Install pavement markers in Marion and Lane counties at various locations between Wilsonville and Cottage Grove, MP 283 to 168. Nighttime lane closures, delays less than 20 minutes. Completion: 9/2009.
 
4. I-5 Pacific Highway — Make improvements to northbound on-ramp at Keubler Boulevard, MP 252. Minor delays. Completion: 9/2010.
 
5. I-5 Pacific Highway — Replace barriers south of Salem, MP 244-249. Single lane closures, minor delays. Completion: 11/2009.
 
6. I-5 Pacific Highway — Lower I-5 northbound lanes at the Santiam (US 20) overcrossing, MP 233-233.4. Intermittent minor delays. Completion:10/2009.
 
7. I-5 Pacific Highway — Rice Hill to Comstock Bridge repairs, MP 148 to 162. Intermittent lane closures. Completion: 2010.
 
8. I-5 Pacific Highway — North Umpqua River Bridge repairs, MP 129. Intermittent nighttime lane closures. Completion: 2010.
 
9. I-5 Pacific Highway — Bridge repair at McLain Avenue and Portland Avenue, MP 121 to 123. Intermittent lane closures. Completion: 2011.
 
10. I-5 Pacific Highway — Shady Bridge replacement, MP 120 to 121. Reduced speed, southbound exit 120 off-ramp closed. Completion: 2010. OTIA
 
11. I-5 Pacific Highway Pave from Booth Ranch to Glendale, MP 80 to 88 NB; MP 98 to 113 NB and SB. Intermittent lane closures; three-day ramp closures at exits 98 and 108. Completion: Summer 2009.
 
12. I-5 Pacific Highway — Pave North Grants Pass to Sexton Summit, MP 58 to 62. Intermittent lane restrictions at night. Completion: 2009.
 
13. I-5 Pacific Highway — Bridge replacement, Louse Creek to Exit 55, MP 55 to 61. Completion: 2010. OTIA
 
14. I-5 Pacific Highway — Bridge construction, Seven Oaks Interchange, exit 35. Intermittent lane restrictions and delays. Completion: 2009. OTIA 
 
15. I-5 Pacific Highway — South Medford Interchange construction, exit 27. Completion: 2010. 
 
16. I-5 Pacific Highway — Neil Creek to Eagle Mill Road bridge replacement, MP 10 to 16. Intermittent delays. Completion: 2009. OTIA
 
17. I-5 Pacific Highway  Pave in Ashland area, MP 11 to 18. Nighttime work, intermittent lane restrictions. Completion: 2009.
 
18. I-5 Pacific Highway — Replace bridge deck, Frontage Road Bridge, MP 4.6. Intermittent lane restrictions and delays. Completion: 2009.
 

Interstate 84
 19. I- 84 Old Oregon Trail Highway — Resurface from MP 342 to 360, construction of truck climbing lane from MP 357 to 360. Lane closures, flaggers at times, minor delays. Completion: 10/2011. OTIA
 
20. I-84 Old Oregon Trail Highway — Repair Lime Interchange bridge, MP 342. Lane closures, traffic pattern changes, minor delays. Eastbound Exit 342 off-ramp closed until 2010 with off-ramp traffic detoured to exit 345. Completion: 11/2010. OTIA
 
21. I-84 Old Oregon Trail Highway — Pave, re-align curve and install variable message signs in the Burnt River Canyon area 12 miles east of Baker City, MP 318 to 347. Lane closures, traffic pattern changes and reduced speeds at various work sites along this corridor. Completion: 11/2010. OTIA
 
22. I-84 Old Oregon Trail Highway — Repair eastbound North Powder railroad overpass bridge, MP 286.2. Lane closures, minor delays. Completion: 11/2009. OTIA
 
23. I-84 Old Oregon Trail Highway — Replace bridge railings in La Grande, MP 261 to 265. Lane closures at various bridge sites. Completion: 11/2009. OTIA
 
24. I-84 Old Oregon Trail Highway — Repair Upper Perry Arch Bridge along dead-end frontage road adjacent to I-84 at MP 254. Lane closures on I-84 to accommodate construction traffic. Completion: 11/2009.
 
25. I-84 Old Oregon Trail Highway — Expand westbound Spring Creek chain-up area at MP 249. Lane closures, minor delays. Completion: 11/2009.
 
26. I-84 Old Oregon Trail Highway — Install rock fall screening adjacent to WB freeway shoulders 10 miles east of Pendleton, MP 220. Lane closures, minor delays. Completion: 11/2009. 
 
27. I-84 Old Oregon Trail Highway — Replace bridge railings in Pendleton, MP 209 to 210. Lane closures at various bridge sites. Completion: 11/2009. OTIA 
 
28. I-84 Old Oregon Trail Highway — Pavement chip seal, repave Swanson - Woelpern Road, Arlington - Tower Road, MP 125 to 159. Daytime and nighttime lane restrictions, minor delays. Completion: Fall 2009.
 
29. I-84 Old Oregon Trail Highway  Replace Fifteen Mile Creek Bridge at east The Dalles city limits, MP 88. Intermittent lane restrictions, minor delays. Completion: Fall 2009.
 
30. I-84 Old Oregon Trail Highway — Concrete joint repair at Fifteen Mile Road, MP 84.2 to 87.9. Intermittent lane closures, minor delays. Completion: Fall 2009.
 
31. I-84 Columbia River Highway — Replace two bridges and repair five bridges between Cascade Locks and Hood River. Occasional daytime lane restrictions. Completion: 10/2010. OTIA
 
32. I-84 Columbia River Highway — Replace one bridge and repair three bridges west of Cascade Locks between mileposts 35.2 and 40.2. Occasional daytime lane restrictions. Completion: 5/2010. OTIA
 
33. I-84 Columbia River Highway — Repave I-84 from Multnomah Falls to Cascade Locks, MP 31.7 to 45.6. Nighttime lane and ramp closures, some daytime lane closures. Completion: 10/2010.
 
34. I-84 Columbia River Highway — Add turn lane on Frontage Road at exit 17. Nighttime lane closures. Completion: 12/2009.

U.S. Highways
35. US 20 Central Oregon Highway — Pavement overlay/chip seal between Harney County line and Hines, MP 84 to 128. Up to 20 minute delays, single lane travel, flaggers, loose rock on the roadway. Completion: 10/2010.
 
36. US 20 Central Oregon Highway — Reconfigure Riley Junction (US 20/US 395) to "T" intersection at MP 104.6. Lane closures, delays up to 20 minute. Completion: 10/2009.
 
37. US 20 Corvallis-Newport Highway — Grind and pave surface, install guardrail, signs, MP 51.4 to 55.8. Night work only. Delays up to 20 minutes. Completion: 9/2009.
 
38. US 20 Corvallis-Newport Highway — Various road improvements from MP 24.5 to 14.5. Single-lane traffic controlled by flaggers and pilot car, delays up to 20 minutes. Completion: 7/2009. 
 
39. US 20/26 Central Oregon Highway — Repair railroad undercrossing in Nyssa, MP 266.5. Road and lane closures, local detours, flaggers, up to 20 minute delays. Completion: 11/2009.
 
40. US 20/26 Central Oregon Highway — Widen highway and add turn lanes at Columbia Avenue intersection two miles north of Nyssa, MP 264.7. Lane closures, flaggers, up to 20 minute delays. Completion: 9/2009.
 
41. US 26 John Day Highway — Replace Kern Creek and Lancaster Creek bridges 15 miles north of Vale, MP 265 to 266. Minor delays, single lane travel controlled with temporary traffic signals. Completion: 11/2009. OTIA
 
42. US 26 John Day Highway — Replace five culverts east of Austin, MP 186 to 189. Minor delays, single lane travel controlled with temporary traffic signals. Completion: 11/2010.
 
43. US 26 John Day Highway — Relocate and reconstruct Sumpter Valley railroad interpretive site parking area and trailhead along highway five miles east of Prairie City, MP 180 to 184. Possible lane closures and flaggers at times. Minor delays. Completion: 10/2009.
 
44. US 26 John Day Highway — Replace John Day River (Coles) Bridge five miles west of John Day, MP 157. Minor delays, single lane travel controlled with temporary traffic signals. Completion: 11/2011. OTIA
 
45. US 26 John Day Highway — Construct/repair curb, sidewalk and storm drain system in Mt. Vernon, MP 154. Up to 20 minute delays, flaggers, lane restrictions. Completion: 7/2009.
 
46. US 26 — Bridge replacement at Marks Creek, MP 34 to 37.4. Detours controlled with traffic lights, minor delays. Completion: Fall 2009.
 
47. US 30 Huntington Highway — Replace Burnt River Bridge between Huntington and I-84 exit 342, MP 4. Minor delays, single lane travel controlled with temporary traffic signals. Completion: 11/2009. OTIA
 
48. US 30 Westgate — Reconstruct Westgate/Court/Dorion Street intersection and at grade railroad crossing; pave Court and Dorian streets in downtown Pendleton. Lane closures, local detours, up to 20 minute delays. Completion: 9/2010.
 
49. US 30 Lower Columbia River Highway — Repair four bridges between St. Helens and Astoria. Occasional nighttime lane restrictions. Completion: 6/2010. OTIA
 
50. US 95 Olds Ferry - Ontario Highway — Replace Snake River Bridge at Weiser, MP 13.7. Up to 20 minute delays, lane restrictions. Completion: 11/2011.
 
51. US 95 ION Highway — Pavement chip seal, MP 13 to 41. Day and nighttime flaggers/pilot cars, lane closures, loose rock on roadway, up to 20 minute delays. Completion: 7/2009.
 
52. US 95 ION Highway — Construct rumble strips, apply durable striping from Idaho border to Burns Junction, MP 0 to 65. Lane closures, flaggers/pilot cars, up to 20 minute delays. Completion: 10/2009.
 
53. US 97 The Dalles-California Highway — Install variable message signs, MP 245.2 to 278.8. Minor delays. Completion: 6/2009.
 
54. US 97  The Dalles-California Highway — Add passing lanes, signing and pavement, MP 229.2 and MP 231.9. Up to 20 minute delays. Completion: 10/2009.
 
55. US 97 — Resurface pavement from Bowery Lane to Romaine Village Way, Bend City Limits. Night work, minor delays. Completion: 10/2009.
 
56. US 97 — Construct two new lanes from Lava Butte to South Century, MP 149 to 153. Minor delays. Completion: Fall 2011.
 
57. US 97 — Resurface pavement from OR 31 to Crescent, MP 169 to 184. Constructing north and southbound passing lanes, signing. Night work, minor delays. Completion: 10/2009.
 
58. US 97 Crooked River Bridge to Redmond. Resurface pavement, install sidewalks in Terrebone, MP 113 to 118. Nighttime paving, daytime construction, minor delays. Completion: Fall 2009.
 
59. US 97 — Add left hand turning lanes at Iris Lane, MP 103 to 104. Minor delays. Completion: 10/2009.
 
60. US 101 Coast Highway — Constitution Way traffic signal project, MP 357 to 362. Constitution Way closed with US 101 lane restrictions and detours for local traffic. Completion: 2009.
 
61. US 101 Coast Highway — Myers Creek Bridge repair, MP 337. Lane restrictions with temporary traffic signal and detours for local traffic. Completion: 2010.
 
62. US 101 Coast Highway — Euchre Creek Bridge replacement, MP 317. Intermittent lane closures. Completion: 2010.
 
63. US 101 Coast Highway — Pave from Bethel Creek to Crystal Creek, MP 285 to 295. Intermittent lane closures. Completion: 2009.
 
64. US 101 Coast Highway — Repair McCullough Bridge, MP 234. Nighttime lane restrictions and delays. Completion: 2011.
 
65. US 101 Coast Highway — Pave from Reedsport to Winchester Bay, MP 211 to 217. Intermittent lane closures. Completion: 2009.
 
66. US 101 Coast Highway — Pave from Lane County line to Smith River, MP 198 to 211. Intermittent lane closures. Completion: 2009.
 
67. US 101  Oregon Coast Highway — Preservation work on Siuslaw River Bridge and lift spans. Occasional one lane closures controlled by flaggers. Minor delays. Completion: 9/2010.
 
68. US 101  Oregon Coast Highway — Paint Alsea Bay Bridge at MP 155.5. Traffic controlled by flaggers, delays up to 10 minutes. Completion: 12/2009.
 
69. US 101 Oregon Coast Highway — Bridge replacement. MP 120.5 Traffic controlled by flaggers, delays up to 10 minutes. Completion 10/2010.
 
70. US 101  Pacific Coast Highway — Reconstruct road from 12th Street to Farmers Creek in Tillamook, MP 66 to 83. Single lane closures, delays of less than 20 minutes. Completion: 9/2010.
 
71. US 101  Pacific Coast Highway — Improvements to intersection with Latimer Road in Tillamook, MP 64. Single lane closures, delays of less than 20 minutes. Completion: 5/2009.
 
72. US 101  Pacific Coast Highway — Highway maintenance north of Manzanita at Necarney Creek/Sam Reed Bride, MP 40. Single lane closures, less than 20 minute delays. Completion: 6/2009.
 
73. US 101  Pacific Coast Highway — Repairs to Youngs Bay Bridge, MP 5. Minor delays, detour. Completion: 5/2009.
 
74. US 101 Pacific Coast Highway — Repaint the north span of Megler Bridge. Single lane closures, delays of less than 20 minutes. Completion: 7/2011.
 
75.US 197 — Highway reconstruction from Burnham Avenue to 3rd Street in Maupin, MP 45. Detours, minor delays. Completion: Spring 2009.
 
76. US 197 — Resurface pavement from The Dalles to Eight Mile Creek, MP 1 to MP 10. Traffic controlled by flaggers, minor delays. Completion: 10/2009.
 
77. US 199 Redwood Highway — Pavement chip seal from Cave Junction to California border. Intermittent delays. Completion: 2009.
 
78. US 395 Pendleton-John Day Highway — Replace McKay Creek Bridge six miles south of Pendleton, MP B5.8. Minor delays. Completion: 11/2011. OTIA
 
79. US 395 Pendleton - John Day Highway — Pavement chip seal from Pilot Rock to Cape Horn, MP B16 to B36. Day and nighttime flaggers/pilot cars, lane closures, loose rock on roadway, up to 20 minute delays. Completion: 10/2009.
 
80. US 395 Pendleton - John Day Highway — Pavement chip seal from Battle Mountain to Fox, MP B42 to B50 and MP B78 to B98. Day and nighttime flaggers/pilot cars, lane closures, loose rock on roadway, up to 20 minute delays. Completion: 10/2009.
 
81. US 395 Pendleton-John Day Highway — Replace Camas Creek and North Fork John Day River bridges near Dale, MP B61 and B64. Minor delays, single lane travel controlled with temporary traffic signals. Completion: 11/2011. OTIA
 
82. US 395 John Day - Burns Highway — Replace Trout Creek Bridge 25 miles north of Burns, MP C43. Minor delays, single lane travel controlled with temporary traffic signals. Completion: 11/2011. OTIA
 
83. US 730 Columbia River Highway — Construct and upgrade sidewalk and bike lanes in Irrigon. Lane restrictions, minor delays. Completion: 11/2009.

Oregon Highways
84. OR 3 Enterprise - Lewiston Highway — Pavement chip seal from Buford Grade to Enterprise, MP 5 to 42.8. Day and nighttime flaggers/pilot cars, lane closures, loose rock on roadway, up to 20 minute delays. Completion: 8/2009.
 
85. OR 6 Wilson River Highway — Slide repair and retaining walls at three locations near the summit from MP 33.2 to 34.2. Daytime flagging and occasional pilot cars to control traffic. Up to 20-minute delays. No weekend work. Completion: 10/2009.
 
86. OR 7 Whitney Highway — Replace two bridges 10 miles west of Baker City, MP 41 to 42. Minor delays, single lane travel controlled with temporary traffic signals. Completion: 11/2010. OTIA
 
87. OR 7 Whitney Highway/Dewey Street — Repair Dewey Street railroad undercrossing in Baker City. Road and lane closures, local detours, flaggers. Up to 20 minute delays. Completion: 12/2009.
 
88. OR 11 Oregon-Washington Highway — Pavement chip seal between Pendleton and Athena, MP 0 to 16.3. Day and nighttime flaggers and pilot cars, lane closures, loose rock on roadway, up to 20 minute delays. Completion: 10/2009.
 
89. OR 18 Salmon River Highway — Improvements at Fort Hill inerchange, MP 24 to 27. Overnight single lane closures Monday through Thursday, delays of less than 20 minutes; Minor delays Monday and Friday evenings. Completion: 11/2009.
 
90. OR 19 John Day Highway — Replace Goose Rock Bridge 10 miles west of Dayville, MP 119. Minor delays, single lane travel controlled with temporary traffic signals. Completion: 10/2011. OTIA
 
91. OR 22 Willamina-Salem Highway — Grind, pave and overlay bridge deck, MP 20.3 to 25.5. Night work only with delays up to 15 minutes. Completion: 10/2009.
 
92. OR 22/Mission Street — Bridge repair on Shelton Ditch. Intermittent lane closures during non-peak hours, minor delays. Completion: 9/2010.
 
93. OR 22 Three Rivers Highway — Slide repair at MP 13. One lane traffic with flaggers. Up to 20 minute delays. Completion: 9/2009.
 
94. OR 22W Willamina-Salem Highway — Pave from OR 18 Junction to 99W, MP 20 to 26. Single overnight lane closures Monday – Thursday with less than 20 minute lane closures; minor delays Friday and Sunday evenings. Completion: 10/2009.
 
95. OR 22E North Santiam Highway — Interchange improvements at Sublimity, MP 12 to 14. Single lane closures, minor delays. Completion: 7/2010.
 
96. OR 31  Fremont Highway — Cattle pass and bridge replacement at MP 102.4, US 395 at MP 126.92. Delays up to 20 minutes. Completion: 10/2009.
 
97. OR 34 Alsea Highway — Pave from MP 46 to 48. One-lane traffic controlled by flaggers. Delays up to 20 minutes. Completion 7/2009.
 
98. OR 36 Mapleton - Junction City Highway — Grind and pave road surface from MP 45.9 to 51.6. One-lane closures with flaggers and pilot cars weekdays only. Up to 20 minute delays. Completion 12/2009.
 
99. OR 38 Umpqua Highway — Pave from Dean Creek to Scottsburg, MP 5 to 17. Intermittent lane closures. Completion 2009.
 
100. OR 38 Umpqua Highway — Charlotte Creek Bridge construction, MP 10.7. Lane closures, temporary traffic signal. Completion: 2009.
 
101. OR 38 Umpqua Highway — Repairs to Mill Creek Bridge, MP 13.2. Lane closures, 24-hour flaggers. Completion: 2009.
 
102. OR 38 Umpqua Highway — Pave from Elkton Slide to Hancock Mountain Road, MP 32 to 39. Intermittent lane closures. Completion: 2009.
 
103. OR 38 Umpqua Highway — Pave from Rock Creek to I-5, MP 53 to 57. Intermittent lane closures. Completion 2009.
 
104. OR 42 Roseburg-Coos Bay Highway — Winston Bridge repair, MP 74. Intermittent lane closures. Completion: 2011.
 
105. OR 62 Crater Lake Highway — Pave from Poplar Drive to Avenue H, White City. Intermittent nighttime lane closures. Completion: 2009.
 
106. OR 66 Green Springs Highway — Hill Creek Culvert replacement, MP 6.6. Intermittent delays. Completion: 2009.
 
107. OR 74 Heppner Highway — Downtown Heppner paving and bridge repair, pavement chip seal from Heppner to junction of US 395, MP 46 to 83. Day and nighttime flaggers/pilot cars, lane closures, loose rock on roadway, up to 20 minute delays. Completion: 10/2009.
 
108. OR 78 Steens Highway — Replace Silvies Slough Bridge east of Burns, MP 0.7. Minor delays, single lane travel controlled with temporary traffic signals. Completion: 11/2011. OTIA
 
109. OR 82 Wallowa Lake Highway — Pavement grind/inlay patching at various locations between Enterprise and Joseph, MP 65 to 72. Lane closures, flaggers/pilot cars, up to 20 minute delays at times. Completion: 8/2009.
 
110. OR 99 Rogue River Highway – Grants Pass. Pave from South Y to Fruitdale, MP 0 to 2.4. Intermittent nighttime lane closures. Completion: 2009.
 
111. OR 99W Pacific Highway West — Signal installation, intersection improvements, MP 26. Intermittent nighttime single lane closures Sunday through Friday. Completion: 10/2009.
 
112. OR 99E Albany-Junction City Highway — Bridge construction and paving, MP 20.6 to 28.2. One-lane traffic controlled by flaggers. Up to 20 minute delays. Completion: 11/2009.
 
113. OR 99E Pacific Highway East — Signal installation, intersection improvements, MP 28. Overnight single lane closures Sunday through Friday. Completion: 4/2010.
 
114. OR 126 Florence – Eugene Highway — Pave 18 miles of Oregon 126 between Phey Lane and Siuslaw River Road, MP 7 to MP 27. Traffic reduced to one lane. 24-hour operations at times. Pilot cars and flaggers will control traffic. Up to 20 minute delays. Completion: 10/2010.
 
115. OR 126 Florence – Eugene Highway — Replace North Fork Siuslaw River Bridge near North Fork Road, MP 1. Occasional one lane closures controlled by flaggers. Traffic will switch to new alignment in fall 2009. Occasional 5-minute delays. Completion: 4/2011.
 
116. OR 138E North Umpqua Highway — Pavement chip seal from Dixonville to Susan Creek, MP 4 to 29. Intermittent lane closures. Completion: 2009.
 
117. OR 138W Elkton-Sutherlin Highway. Pave MP 0 to 9. Intermittent lane closures. Completion: 2009.
 
118. OR 140 Lake of the Woods Highway — Pave from MP 0 to 8. Intermittent lane closures with delays. Completion: 2009.
 
119. OR 140W Lake of the Woods Highway — Pave, install guardrail and signs, MP 30.9 to MP 41.4. Delays up to 20 minutes. Completion: 10/2009.
 
120. OR 140E  Klamath Falls-Lakeview Highway — Recycle asphalt pavement, install guardrail, drainage and sidewalks, MP 34.4 to MP 54.1 Delays up to 20 minutes. Completion: 10/2009.
 
121. OR 194 Monmouth Highway — Pave road surface, MP 5 to 6. One-lane traffic controlled by flaggers. Delays up to 20 minutes. Completion 7/2009.
 
122. OR 207 Lexington-Echo Highway — Pavement chip seal between I-84 at Stanfield Interchange/exit 188 and Morrow County line, MP 19.8. Day and nighttime flaggers/pilot cars, lane closures, loose rock on roadway, up to 20 minute delays. Completion: 7/2009.
 
123. OR 219 Hillsboro-Silverton Highway — Pavement patching from Scholls to Newberg, MP 10 to 19. Intermittent lane closures, less than 20 minute delays. Completion: 10/2009.
 
124. OR 226 Albany-Lyons Highway — Pavement chip seal between Albany and Lyons, MP 0 to 13. Flaggers will control traffic. Up to 20 minute delays. Completion: 9/2009.
 
125. OR 229 Siletz Highway — Pave four miles of OR 229, MP 19 to 23. Flaggers will control traffic. Up to 20 minute delays. Completion 7/2009.
 
126. OR 229 Siletz Highway — Slide repair at MP 5.2. One lane traffic with flaggers. Up to 20 minute delays. Completion: 7/2009.
 
127. OR 233 Lafayette Highway — Pavement crack sealing, safety improvements, MP 0 to 6. Intermittent lane closures, less than 20 minute delays. Completion: 10/2009.
 
128. OR 233 Amity-Dayton Highway — Pavement chip seal, MP 3 to 7. Intermittent lane closures, less than 20 minute delays. Completion: 10/2009.
 
129. OR 238 Jacksonville Highway — Pave in Grants Pass from South Y to Jaynes, MP 0 to 4. Intermittent nighttime lane closures. Completion 2009.
 
130. OR 240 Yamhill-Newberg Highway — Pavement overlay and patching, MP 1 to 10. Intermittent lane closures, less than 20 minute delays. Completion: 10/2009.
 
131. OR 331 Umatilla - Mission Highway — Construct turn lane refuges for local business access between I-84 at exit 216 and the Wildhorse Resort, MP 0 to 1. Lane closures, flaggers, delays up to 20 minutes. Completion: 11/2009. OTIA
 
132. OR 395 Fremont Highway — Pavement, curve improvements and install sidewalks, MP 127.5 to MP 128.2, MP 142.6 to MP 143 and MP 144.2 to MP 145.1. Occasional minor delays. Competion: 10/2009.
 
133. OR 569 Beltline Highway — Rebuild freeway ramp at Coburg Road interchange, install illumination, traffic signals. MP 10.9 to 11.9. Nighttime lane closures. One lane open in each direction at all times at night. 10 minute delays. Completion: 11/2009.
 
141. OR 242 Old McKenzie Highway — Repave approximately 15 miles of roadway. Closed to traffic. Completion: 8/2009.

Other Roads
 134. Route 402 Kimberly-Long Creek Highway — Replace John Day River Bridge in Monument, MP 13.06. Flaggers, minor delays with single-lane travel at work site. Completion: 8/2009.
 
135. Frontage Road (Union County) — Repair Upper Perry Arch Bridge located along dead-end frontage road adjacent to I-84 MP 254. Bridge closed, no detour. Lane closures on I-84. Completion: 11/2009.
 
136. D Street (Baker City) — Extend and improve D Street in Baker City. Road closures, local detours, flaggers, up to 20 minute delays. Completion: 11/2009. OTIA
 
137. Birch Street (Baker City) — Rebuild Birch Street in Baker City. Road closures, local detours, flaggers, up to 20 minute delays. Completion: 11/2009.
 
138. Oregon Street (Ontario) — Rebuild Oregon Steet in Ontario. Road closures, local detours, flaggers, up to 20 minute delays. Completion: 11/2010.
 
139. Airport Road (Burns) — Replace Nine Mile Slough Bridge. Road closures, local detours, flaggers, up to 20 minute delays. Completion: 11/2009. OTIA
 
140. West Loop Road (Burns) Replace Silvies River Bridge. Road closures, local detours, flaggers, up to 20 minute delays. Completion: 11/2009. OTIA

Portland Area Projects
/ODOT/COMM/images/2009ConstMap-550.jpg
1. I-5 Pacific Highway — Widening to three lanes, adding shoulders from Victory Boulevard to Lombard Street (Delta Park Project). Nighttime lane closures. Completion: 11/2010.
 
2. I-5 Pacific Highway — Paving from MP 289.8 to 283 (Tualatin River to Willamette River), widening the Nyberg Road off-ramp from I-5 south, adding north and southbound auxiliary lanes, building new sound wall. Nighttime lane closures. Completion: 12/2010.
 
3. I-205 East Portland Freeway — Replace joints on the north portion of the Glenn Jackson Bridge MP 25.61 to 27.18. Nighttime single lane closures. Weekend double lane closures 24/7. Completion: 2010.
 
4. I-205 East Portland Freeway — Repair joints and pave the Willamette River (George Abernethy) Bridge MP 8.78 to 9.28. Nighttime single lane closures, 24/7 weekend double lane closures, intermittent ramp closures. Completion: 10/2009.
 
5. I-405 Stadium Freeway — Repave I-405 from MP .04 to 4.21 (Fremont Bridge to the Marquam Bridge) Replace lighting and improve signage along the corridor. Nighttime lane closures, weekend full directional closures (opposite direction will remain open during full directional closure). Nighttime ramp closures and tunnel closures. Completion: 12/2009.
 
6. US 26 Sunset Highway — Paving and installing cable barrier from 185th to Glencoe Road, MP 64.3 to 57.2. Nighttime lane closures. Completion: 11/2010.
 
7. US 30 Lower Columbia River Highway — Improving sidewalks and repaving Yeon from MP 1.9 to 3.9. Nighttime lane closures from 7 p.m. to 5:30 a.m. Completion: 10/2009.
 
8. OR 99W Pacific Highway West — Installing new and improving existing sidewalks in five locations on Highway 99W from 64th Avenue to Canterbury Lane, MP 7 to 10.8. Nighttime lane closures. Completion: 6/2009.
 
9. OR 99E Pacific Highway East — MLK/Grand UPRR overcrossing. Replacing north and southbound viaducts from MP 1.0 to 1.25. Nighttime lane closures, closure of Division Street on-ramp to 99E northbound. Completion: 2/2011.
 
10. OR 99E Pacific Highway West — Paving and striping to provide continuous left turn refuge, upgrading signs and guardrails in Oregon City from MP 13.8 to 15.2. Lane closures. Completion: 11/2009.
 
11. OR 213 Cascade Highway South — East Portland Freeway to Conway Drive, paving roadway and installing signals from MP 0 to 4.0. Intermittent lane closures from 6 a.m. to 3:30 p.m. Completion: 11/2009.
 
12. OR 217 Beaverton – Tigard Highway — Widening to three lanes from MP 0 to 1.47 (US 26 Sunset Highway to OR 8 Tualatin Valley Highway), lengthening the Wilshire Street overpass, paving US 26 - OR 217 interchange, and other improvements. Nighttime lane closures. Completion: 2011. OTIA
 
13. OR 224 Clackamas Highway  Paving and making improvements to the center median, sidewalk, and shoulder in Estacada from MP 17.8 to 23.4. Minor delays. Completion: 2011.

Road Project Hotlines
/ODOT/COMM/images/2009ConstMap-550.jpg
 
 
 
 
 
 
  • (800) 977-6368 (in-state callers only)
  • (503) 588-2941 (out-of-state callers)
  • 511 or www.TripCheck.com 
For questions or comments about ODOT, call (888) ASK-ODOT (275-6368) or visit Ask ODOT on the Web.
 
For information about the Oregon Department of Transportation, visit www.Oregon.gov/ODOT
 
Page updated: May 22, 2009