South Mist Pipeline Extension
Facility:
62 mile, 24-inch natural gas pipeline
 
Location: Washington, Clackamas and Marion Counties
 
Status:  Operating.
 
Certificate Holder:
Northwest Natural
 
Contact:
Gary Bauer
Northwest Natural
220 NW Second Ave.
Portland OR 97209
 
503-220-2403
 
Department of Energy staff: Adam Bless 
 
Original site certificate signed: March 21, 2003
 
Current site certificate: Fourth Amended Site Certificate (issued July 27, 2007)
 
History:
  • September 30, 1999: Notice of intent submitted 
  • March 29, 2000: Department of Energy issued a project order
  • March 22, 2001: Application submitted
  • September 24, 2001: Application complete (date of filing)
  • July 10, 2002: Department of Energy issued a draft proposed order.
  • September 19, 2002: Department of Energy issued a proposed order.
  • March 13, 2003: Council approved a site certificate
  • June 5, 2003:  Request for Amendment #1 received.
  • July 11, 2003: Department of Energy issued proposed order on Amendment #1
  • August 28, 2003: Council approved Amendment #1
  • September 12, 2003: Request for Amendment #2 received
  • September 30, 2003: Department of Energy issued a proposed order on Amendment #2
  • October 8, 2003: Council approved Amendment #2 (temporary order)
  • December 5, 2003: Council adopted a final order on Amendment #2
  • February 18, 2004: Request for Amendment #3 received
  • March 19, 2004: Department of Energy issued a proposed order on Amendment #3
  • April 23, 2004: Council approved Amendment #3
  • April 25, 2007: Request for Amendment #4 received.
  • June 22, 2007: Department of Energy issued a proposed order on Amendment #4
  • July 27, 2007: Council approved Amendment #4.
 